The difference between construction management and contractor led procurement routes
Construction management is a procurement route in which works are constructed by a number of different trade contractors, these trade contractors are contracted to the client but managed by a construction manager, who is appointed early in the design process to improve the buildability and packaging of proposals as they develop. The construction manager acts as an agent for the client, administering and co-ordinating the works contracts.
A contractor led procurement route is similar in that the contractor side has a key management role, however in contractor lead procurement the contractor provides a design team to develop a concept design as proposals for a tendering process. Typically this leads to two teams proceeding to Stage 3, where assessments are finalised, and one construction team is appointed as the preferred bidder.
[edit] Related articles on Designing Buildings
- Admeasurement.
- Bill of quantities.
- Construction manager.
- Contract conditions.
- Contractor led procurement route.
- Contract sum.
- Defined provisional sum.
- Difference between preliminaries and preambles.
- Prime cost sum.
- Procurement route.
- Provisional sum.
- The difference between admeasurement and construction management contracts.
- The difference between a prime cost sum and a provisional sum.
- Undefined provisional sum.
- Variations.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.